Singapore Coal Monthly – No sign of unwinding China’s import restriction April 25, 2019 738

PSR Recommendation: BUY Status: Maintained
Target Price: S$0.300

China

144mn tonnes of new capacity added in 1Q19

National Development and Reform Commission and associated authorities approved the resumption of work for 29 mines with a total capacity of 177mn tonnes, and 144mn tonnes of which were new capacities in 1Q19. The mines are mainly located in North and Northwest China, producing thermal coal.

 

Expecting 30% growth of domestic coal transport capacity by rail

In Apr-19, China Railway Economic and Planning Research Institute announced that the coal transportation capacity by railway would increase 650mn tonnes to 2.8bn tonnes (75% of the national production) or have a 30% growth by 2020. Coal production will continue to be consolidated within Shanxi, Shannxi, and western part of Inner Mongolia.

 

Indonesia

Firmer approach to ensure domestic obligation is met

According to the interview with the Indonesian Coal Mining Association’s executive director by S&P Global Platts, the government wants to closely control the production output for the first time. However, there is difficulty in implementing the policy due to the lack of coordination between the local governments. The DMO requirement for 2019 could be higher than 25% which was the quota for 2018.

 

China boosted domestic coal supply, associating with import restriction

The restriction on seaborne coal remains. Apart from Australian coal, the clearance for Indonesian coal at northeastern China ports was delayed in Apr-19. China has been reducing its reliance on coal imports which reached a 5-year peak of 281mn tonnes last year. Domestic coal demand is growing at a milder pace, in line with the overall economy in China. The tactical increase in supply and transportation capacity is to supplement the shortfall due to the reduction of coal import and narrow the price gap between land-borne and seaborne coal respectively. However, the strategic clampdown on coal production and consumption will carry on domestically.

 

The mitigation of price headwinds throughout the Indonesian approach is limited 

Coal selling price is more critical for business operation and performance. The current unfavourable price hampers the ramp-up of production given the thinner margin that miners will now suffer.  The DMO imposes sales quota and a price cap. So it has little help on reliving pressures from operational difficulties.

 

Coal counters monthly updates

Golden Energy and Resources (Target px: S$0.30 / BUY)

  • Expect 25mn tonnes of production in 2019 (up 10.6% YoY)
  • Expect cash cost to revert to US$25/tonne (down 8.8 % YoY)
  • Higher production and lower cash cost could offset the price headwind

 

Geo Energy Resources (Target px: S$0.22/ ACCUMULATE)

  • Expect flattish 8mn tonnes of production in 2019
  • Cash cost will be slightly lower this year
  • Potential deployment of cash to acquire a mine

 

Investment action

We are still positive on the sector. The ramp-up of production is expected to be moderate for each of the two coal counters this year while the expected average coal price (4,200 GAR: US$ 39.5/tonne) in 2019 will be 10% lower than that in 2018. Meanwhile, the cash cost will also decline due to the normalisation of stripping ratio. Therefore, the overall performance could slightly improve because of margin improvement. We maintain the OVERWEIGHT rating on the coal sector.

 

Peer comparison

Coal reserve estimate was as of 2016

*Agritrade Resources: financial year ends in March, and coal reserve estimate was as of Mar-18           

**Harum Energy: coal reserve estimate was as of 2009                                                                                          

***Baramulti Suksessaran: coal reserve estimate was as of 2012

 

Phillip Coal Tracker: Our snapshot of coal markets

Figure 1: Monthly coal production in PRC grew slightly

Source:  National Bureau Statistics of PRC, PSR

 

Figure 2: Growing coal import from Indonesia to China

Source: Bloomberg, PSR

 

Figure 3: China hydro power supply spiked YoY in Mar-19                     

Source:  National Bureau Statistics of PRC, PSR 

 

Figure 4: HBA dropped to a 20-month low

Source: Coalspot.com, PSR

 

Figure 5: Qinhuangdao 5,500 GAR weekly FOB spot price

Source: Bloomberg, PSR, NDRC price zones (red/blue/green)                                                    

 

Figure 6: Total port coal inventory declined recently

*Source: Bloomberg, PSR

 

*The total port coal inventory includes coal stockpile at Qinghuangdao Port, Tianjin Port, Caofeidian Port, Guangzhou Port, Jingzhou Port, Lianyungang Port, Dandong Port, Jingtang Port, Yinkou Port, Qingdao Port, and Huanghuagang Port.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments

About the author

Profile photo of Chen Guangzhi

Chen Guangzhi
Investment Analyst
Phillip Securities Research Pte Ltd

Guangzhi graduated from Singapore Management University with a Master degree in Applied Finance and from South China University of Technology with a Bachelor degree in Electronic Commerce.

The current sector coverages include Energy, Utilities, and Mining sectors. He has 3 years experience in equity research in both Hong Kong and Singapore market. He is the mandarin spokesperson for Phillip Securities Research in relation to China-related projects and all mandarin seminars and client events.

Get access to all the latest market news, reports, technical analysis
by signing up for a free account today!